Project Photos
(Click HERE to view final building pictures.)
Phase 1
April – May 2019: Demolition
May – June 2019: Demolition
June – July 2019: Demolition, Concrete Prep, Plumbing, HVAC
July – August 2019: Concrete Prep, Plumbing, HVAC – continued-
August – September 2019: Concrete, HVAC Completion, Demo for Children’s Wing
September – October 2019: Framing, Concrete, Children’s Wing Addition
October – November 2019: Framing, Concrete, Electrical, Plumbing, Drywall, Glass, Children’s Wing
November – December 2019: Concrete, Electrical, Plumbing, Drywall, Glass, New Entrances
December 2019: Children’s Wing Framing, Study Rooms, Glass Installation, Dry Wall, Staff Area, New Entrances
Phase 2
January 2020 – March 2020: Moved Collection to Phase 1, Staff Work Area Completed, Demolition Phase 2, New Addition Glass Complete, HVAC Complete, New Roof Complete
April – May 2020: Children’s Wing Addition, Demo Old Entrance, Glass and Panel Installation
May – July 2020: Continued Interior Work, Exterior Concrete
July – August 2020: Continued Interior Work, Exterior Concrete, Furniture and Shelving Installation
August – September 2020: Flooring, Restrooms, Exterior Paving, Exterior Finishings, Furniture and Shelving Installation
September – October 2020: Finishing Touches